The best efforts have been made so that the data and material published in this site reflect actual administrative norms and practices.
Nevertheless, the entities mentioned in thesite are not responsible for its exactness and expressly deny any responsibility for the damages that would stem form use of the information from this site or use of the site itself. The site contains links to other web pages that are not the responsibility of the entities mentioned in the site.
By consulting this site, the user grants the most complete and irrevocable waiver to all entities mentioned in the site, freeing them absolutely from any kind of responsibility, and agrees to refrain from any action or claim.
Please copy/paste the following html code inside your page:
<iframe style="height: 100%; border:none; width: 100%;min-height: 400px;" src="https://armenia.eregulations.org/procedure/32/step/175?l=en&embed=true&includeSearch=true"></iframe>
Please copy/paste the following html code inside your page:
<iframe style="height: 100%; border:none; width: 100%;min-height: 400px;" src="https://armenia.eregulations.org/EmbedSearch?l=en&embed=true&includeSearch=true"></iframe>
Time frame ( in detail ) |
Waiting time until next step |
||||
|
|
Mon: | 09:00 - 18:00 |
Tue: | 09:00 - 18:00 |
Wed: | 09:00 - 18:00 |
Thu: | 09:00 - 18:00 |
Fri: | 09:00 - 18:00 |
If the length of the new system of water supply or sewer systems separately exceeds 500 meters and (or) a pumping station is required, the maximum period of time for receiving Service Delivery Contract shall not exceed 120 business days.
The applicant and Utility Provider may fix different time frame in the Connection Contract for Service Delivery Contract.
In case of failure to submit the documents to the Provider within the prescribed time period, the offer of signing a Connection Contract will be rejected by the Provider.
After receiving the Connection Contract and 80% prepayment, the Utility Provider starts construction works for the new water system within prescribed time frame.