Steps (18) arrow_drop_up arrow_drop_down
Apply for Design Permit (Architectural-Planning Assignment)  (3) expand_more expand_less
Get confirmation for Design documents and apply for Construction Permit  (6) expand_more expand_less
Notify the Municipality of Yerevan about the start of construction works  (1) expand_more expand_less
Form Acceptance Committee and involve members  (4) expand_more expand_less
Apply for Certificate of Completion (Commissioning Permit)  (4) expand_more expand_less

arrow_drop_up arrow_drop_down
Summary of the procedure

Institutions involved 4 expand_more expand_less

Any licensed designing company
Any licensed expertise company of urban development documents
Acceptance Committee

Results 2 expand_more expand_less

Construction Permit
Certificate of Completion (Commissioning Permit)

Required Documents expand_more expand_less

Application form (architectural-constructional assignment)
Extract from state register agency (x 8)
Property ownership certificate
Plot plan
Supply Contract
Application for construction permit
Design Documents
Expertise Statement
Payment Receipt
Statement about the start of construction works
Application to Involve Yerevan Municipality Representative
Execution documents (x 2)
Signatures of Acceptance Committee Members
Account numbers of administrative districts of Yerevan
Application for Certificate of Completion (Commissioning Permit)
Acceptance Committee Act
Payment receipt for Certificate of Completion
Payment receipt for Commissioning Permit

Estimated cost AMD  150,000

expand_more expand_less

AMD expand_more expand_less
  • AMD Add Name Here
AMD 75,000
AMD 50,000
AMD 25,000

Total Duration 15d - 59d  expand_more expand_less

  Min. Max.
Total time (sum): 15d 59d
of which:
Waiting time in queue (sum): 50mn 2h. 20mn
Attention at counter: 50mn 1h. 40mn
Waiting time until next step (sum): 14d 59d

Laws 8 expand_more expand_less

Certificate of Completion (Commissioning Permit) - Guide (ARM) Certificate of Completion (Commissioning Permit) - Guide (ARM)
Council of the Elders Decision N 89-N as of 26.12.2017 Council of the Elders Decision N 89-N as of 26.12.2017 (ARM)
Council of the Elders Decision N 91-N as of 26.12.2017 Council of the Elders Decision N 91-N as of 26.12.2017 (ARM)
Council of the Elders Decision N224 -N as of 06.05.2011 Council of the Elders Decision N224 -N as of 06.05.2011 (ARM)
Design Documentation & Construction Permit Guide (ARM) Design Documents & Construction Permit - Guide (ARM)
Planning Permission (Architectural-Planning Assignment) Guide (ARM) Design Permit (Architectural-Planning Assignment) - Guide (ARM)
Government of the Republic of Armenia Decision N 596-N as of 19.03.2015 (ARM) Government of the Republic of Armenia Decision N 596-N as of 19.03.2015 (ARM)
Statement Notifying About the Start of Construction Works - Guide (ARM) Statement Notifying about the Start of Construction Works - Guide (ARM)