Steps (18) arrow_drop_up arrow_drop_down
Apply for Design Permit (Architectural-Planning Assignment)  (3) expand_more expand_less
Get confirmation for Design documents and apply for Construction Permit  (6) expand_more expand_less
Notify the Municipality of Yerevan about the start of construction works  (1) expand_more expand_less
Form Acceptance Committee and involve members  (4) expand_more expand_less
Apply for Certificate of Completion (Commissioning Permit)  (4) expand_more expand_less

14
Receive Acceptance Committee Act on completed construction
(last modified: 25/02/2020)

Waiting time until next step

 -  10 days

Contact details

Entity in charge

Acceptance Committee


Expected results

Acceptance Committee Act

Requirements

1. Execution documents
Execution documents
2. 01 - Libre deuda de patente
Signatures of Acceptance Committee Members

Time frame

The developer shall, within a 10 day period after having the Act signed by the Acceptance Commission, apply to the Municipality for obtaining a Certificate of Completion (Commissioning Permit)
Waiting time until next step: Max.   10 days

Legal justification

1. Government of the Republic of Armenia Decision N 596-N as of 19.03.2015 (ARM)
Government of the Republic of Armenia Decision N 596-N as of 19.03.2015 (ARM)
2. Certificate of Completion (Commissioning Permit) - Guide (ARM)
Certificate of Completion (Commissioning Permit) - Guide (ARM)

Additional information

Conformity of the completed project with the Design and standard technical documents shall be approved by the Act of the Acceptance Committee and substantiated by an execution document or positive opinions on the technical condition of the project.

The act of the Acceptance Committee shall be signed and sealed (if the seal is available) by all members.

The package of execution documents is drawn up by the contractor with the participation of the persons carrying out technical supervision or in cases provided for by the contract — copyright supervision. In case of unavailability of the package of execution documents or a part thereof, the contractor shall be obliged to restore them at his or her own expense by carrying out necessary technical expert reviews or tests.

Powered by eRegulations ©, a content management system developed by UNCTAD's Business Facilitation Program and licensed under Creative Commons License