Apply for Design Permit (Architectural-Planning Assignment)  (3) expand_more expand_less
Get confirmation for Design documents and apply for Construction Permit  (6) expand_more expand_less
Notify the Municipality of Yerevan about the start of construction works  (1) expand_more expand_less
Form Acceptance Committee and involve members  (4) expand_more expand_less
Apply for Certificate of Completion (Commissioning Permit)  (4) expand_more expand_less

9
Obtain Construction Permit
(last modified: 25/02/2020)

Time frame ( in detail )

Waiting time until next step

10 mn  -  25 mn
 -  0.5 day

Contact details

Entity in charge

Yerevan Municipality

1 Argishti St, Yerevan 0015
Tel: +374 11 514 000
Email: info@yerevan.am
Website: https://www.yerevan.am/en/
Directions: Google maps

Unit in charge

One Window Office

Mon: 09:00 - 13:00, 14:00 - 18:00
Tue: 09:00 - 13:00, 14:00 - 18:00
Wed: 09:00 - 13:00, 14:00 - 18:00
Thu: 09:00 - 13:00, 14:00 - 18:00
Fri: 09:00 - 13:00, 14:00 - 18:00

Person in charge

One Window Desk Officer

Expected results

Construction Permit

Requirements

1. 01 - Libre deuda de patente
Passport
or 01 - Libre deuda de patente
National ID card
In case of a representative
1. Power of attorney
Power of attorney
2. 01 - Libre deuda de patente
Passport or ID card of the representative

Time frame

Waiting time in queue: Min.   5mn - Max.  15mn
Attention at counter: Min.   5mn - Max.   10mn
Waiting time until next step: Max.   0.5 day

Legal justification

1. Government of the Republic of Armenia Decision N 596-N as of 19.03.2015 (ARM)
Government of the Republic of Armenia Decision N 596-N as of 19.03.2015 (ARM)
2. Design Documents & Construction Permit - Guide (ARM)
Design Documents & Construction Permit - Guide (ARM)

Additional information

Construction permit is a document which approves the developer’s right to carry out certain construction works both on a land parcel provided for new development and in the existing buildings and structures.

Construction permit comes into force the next day following the day of receiving the permit by the applicant or its representative.

Construction duration is defined in the construction permit, however, it should not exceed 1.5 times of the construction period based on the design documentation in case of newly built buildings.

Where the construction of the newly built projects is impossible to carry out without demolition of the building (structure) located on the given land parcel, the construction permit, with a relevant note, shall be also a demolition (or dismantlement) permit.

Construction permit is not required for the construction of I category building sites - such as internal decoration, landscaping and other small-scale construction works that can be carried out by the real estate owner without any design and construction permits.

Recourse: Yerevan Municipality

Entity in charge

Yerevan Municipality

1 Argishti St, Yerevan 0015
Tel: +374 11 514 000
Email: info@yerevan.am
Website: https://www.yerevan.am/en/
Directions: Google maps

Unit in charge

"Hot Line" Service

Mon: 09:00 - 18:00
Tue: 09:00 - 18:00
Wed: 09:00 - 18:00
Thu: 09:00 - 18:00
Fri: 09:00 - 18:00
Sat: 09:00 - 18:00
Sun: 09:00 - 18:00

Person in charge

"Hot Line" Service Employee

Tel: 1-05 / + 374 (11) 514-000