5
Receive an offer to sign the Supply Contract
(last modified: 25/02/2020)

Waiting time until next step

 -  5 days

Contact details

Entity in charge

"GAZPROM ARMENIA" CJSC

Charentsi St., 141/3 Building (Kentron adm. district), Yerevan 0025
Tel: +374-10-570307
Email: contact@gazpromarmenia.am
Website: https://armenia.gazprom.com
Directions: Google maps

Time frame

After completion of construction works and final calculations, the applicant receives an offer to sign 2 copies of Supply Contract and pay the remaining connection fee.

The Applicant should submit to the Provider one copy of the signed Contract within 5 business days after receiving it, together with a copy of the payment receipt of the unpaid part of the connection fee.

Waiting time until next step: Max.   5 days

Legal justification

1. Public Services Regulatory Commission (PSRC) decision N95-N as of 08.07.2005 (ARM)
Public Services Regulatory Commission (PSRC) decision N95-N as of 08.07.2005 (ARM)

Additional information

After the applicant signs the Connection Contract, the maximum period of time for receiving Contract shall not exceed maximum 90 business days (if the applicant is a non-domestic consumer organization) or maximum 120 business days (if the applicant is a developer of a newly constructed building or district).