Apply for planning permission (architectural-planning assignment)  (3) expand_more expand_less
Get confirmation for design documentation and apply for construction permit  (6) expand_more expand_less
Notify the Municipality of Yerevan of the start of construction works  (1) expand_more expand_less

10
Submit a statement about the start of construction works
(last modified: 26/07/2019)

Timeframe ( ver detalles )

Espera hasta paso siguiente

10 mn  -  25 mn
3 days  -  0 days

Contact details

Entity in charge

Yerevan Municipality

1 Argishti St , Yerevan 0015
Tel: +374 11 514 000
Email: info@yerevan.am
Website: https://www.yerevan.am/en/
Directions: Google maps

Unit in charge

One Window Office

Mon: 09:00 - 13:00, 14:00 - 18:00
Tue: 09:00 - 13:00, 14:00 - 18:00
Wed: 09:00 - 13:00, 14:00 - 18:00
Thu: 09:00 - 13:00, 14:00 - 18:00
Fri: 09:00 - 13:00, 14:00 - 18:00

Person in charge

One Window Desk Officer

Requirements

1. Statement about the start of construction works
Statement about the start of construction works

Time frame

At least 3 days before the start of the construction works in accordance with the construction permit, the developer should submit a statement to Yerevan Municipality.
Waiting time in queue: Min.   5mn - Max.  15mn
Attention at counter: Min.   5mn - Max.   10mn
Waiting time until next step: Min.   3 days

Legal justification

1. Government of the Republic of Armenia Decision N 596-N as of 19.03.2015
Government of the Republic of Armenia Decision N 596-N as of 19.03.2015

Additional information

If during the construction works changes occur in the details of the Construction Permit or submitted statement, the developer, within 5 days, should resubmit a statement to the Municipality informing about the relevant changes.

Once the statement about the start of the construction works is received by the Municipality, it is sent to the Urban Planning State Inspectorate within 3 days.

In case the developer does not notify the Municipality about the start of the construction works within the established time frame, construction permit will be temporarily suspended.