Summary print

Preview & Print

Properties

Steps (18) arrow_drop_up arrow_drop_down
Apply for Design Permit (Architectural-Planning Assignment)  (3) expand_more expand_less
Get confirmation for Design documents and apply for Construction Permit  (6) expand_more expand_less
Notify the Municipality of Yerevan about the start of construction works  (1) expand_more expand_less
Form Acceptance Committee and involve members  (4) expand_more expand_less
Apply for Certificate of Completion (Commissioning Permit)  (4) expand_more expand_less

10
Submit a statement about the start of construction works
(last modified: 25/02/2020)

Time frame ( in detail )

Waiting time until next step

10 mn  -  25 mn
3 days  - 

Contact details

Entity in charge

Yerevan Municipality

1 Argishti St, Yerevan 0015
Tel: +374 11 514 000
Email: info@yerevan.am
Website: https://www.yerevan.am/en/
Directions: Google maps

Unit in charge

One Window Office

Mon: 09:00 - 13:00, 14:00 - 18:00
Tue: 09:00 - 13:00, 14:00 - 18:00
Wed: 09:00 - 13:00, 14:00 - 18:00
Thu: 09:00 - 13:00, 14:00 - 18:00
Fri: 09:00 - 13:00, 14:00 - 18:00

Person in charge

One Window Desk Officer

Requirements

1. Statement about the start of construction works
Statement about the start of construction works
2. Extract from state register agency
Extract from state register agency
3. 01 - Libre deuda de patente
Passport
or 01 - Libre deuda de patente
National ID card
In case of a representative
1. Power of attorney
Power of attorney
2. 01 - Libre deuda de patente
Passport or ID card of the representative

Time frame

At least 3 days before the start of the construction works in accordance with the construction permit, the developer should submit a statement to Yerevan Municipality.
Waiting time in queue: Min.   5mn - Max.  15mn
Attention at counter: Min.   5mn - Max.   10mn
Waiting time until next step: Min.   3 days

Legal justification

1. Government of the Republic of Armenia Decision N 596-N as of 19.03.2015 (ARM)
Government of the Republic of Armenia Decision N 596-N as of 19.03.2015 (ARM)
2. Statement Notifying about the Start of Construction Works - Guide (ARM)
Statement Notifying about the Start of Construction Works - Guide (ARM)

Additional information

The statement should include information about the contractor as well as companies, which perform technical and copyright supervision over the construction.

If during the construction works changes occur in the details of the Construction Permit or submitted statement, the developer, within 5 days, should resubmit a statement to the Municipality informing about the relevant changes.

Once the statement about the start of the construction works is received by the Municipality, it is sent to the Urban Planning State Inspectorate within 3 days.

In case the developer does not notify the Municipality about the start of the construction works within the established time frame, construction permit will be temporarily suspended.

Recourse: Yerevan Municipality

Entity in charge

Yerevan Municipality

1 Argishti St, Yerevan 0015
Tel: +374 11 514 000
Email: info@yerevan.am
Website: https://www.yerevan.am/en/
Directions: Google maps

Unit in charge

"Hot Line" Service

Mon: 09:00 - 18:00
Tue: 09:00 - 18:00
Wed: 09:00 - 18:00
Thu: 09:00 - 18:00
Fri: 09:00 - 18:00
Sat: 09:00 - 18:00
Sun: 09:00 - 18:00

Person in charge

"Hot Line" Service Employee

Tel: 1-05 / + 374 (11) 514-000
Powered by eRegulations ©, a content management system developed by UNCTAD's Business Facilitation Program and licensed under Creative Commons License